Northern Line Extension works at Kennington Green
Northern Line Extension (NLE) Works Site at Kennington Green At the end of March, the acoustic enclosure at Kennington Green will be taken down. This process will start at the end of March and take approximately five weeks to complete. Following the removal of the acoustic enclosure, the next phase of works will involve the construction of the basement structures for the Head House. Between April and June 2018, the concrete slab located on Kennington Green will be removed 16 metres underground will then be excavated for the basement. Construction of the basement taking place between June 2018 and January 2019. It will be necessary to move the line of the hoardings out temporarily, although footpath access will remain. It will also be necessary to reopen the road barrier to Montford Place, (outside the Beefeater entrance) to allow access to properties. 24/7 working will continue underground, however above ground…